Citigroup

Project Type: Office

  • Citigroup Las Colinas

How fast can you complete a project from site selection to move-in? That was the challenge that Citigroup brought to KDC. And it turns out that the answer is 7 ½ months. By forming a design-build development team, KDC was able to implement all aspects of site selection, due diligence, programming, design, and construction on an accelerated schedule. The “float” time was removed from all the schedules, and the projects came in on time and under projected budgets.

  • 80% Raised Flooring
  • 24/7 Customer Service
  • Back-up Electric Power
  • Redundant Fiber Optics Along Diverse Paths
  • Cafeteria

Broker: Cushmman & Wakefield
Architect: Corgan
Contractor: Austin Commercial

Fast Facts

Schedule

7.5 Months

Size

442,897 SF

Location

Irving, TX